Creating a cost surface raster

Cost distance tools calculate for each cell the least accumulative cost to specified source locations over a cost surface. A source and a cost dataset must first be created. These datasets can be created in different ways with the tools available in the ArcGIS Spatial Analyst extension.

Creating a multi criteria cost surface

In the following example, a least-cost path on which to construct a new road is needed. To create the path, first a cost distance surface must be created, which requires a source location dataset and a cost raster as inputs. The example will demonstrate creating a cost raster.

The source

The source is the starting point of your proposed feature for analysis. In the graphic below, you can see the area identified as the starting location (in red) for the proposed road.

Source area
Source area to determine least cost distance from

The cost raster

A cost raster identifies the cost of traveling through each cell. To create this raster, you need to identify the cost of constructing a road through each cell. Although the cost raster is a single dataset, it is often used to represent several criteria. In this example, land use and slope influence the construction costs. Each of these datasets is in a different measurement system (land-use type and percent slope), so they cannot be directly compared to one another and must be reclassified to a common scale.

Creating a cost raster

In this example there are three general steps to create a cost raster.

Reclassifying your datasets to a common scale

The slope and land-use rasters have been reclassified on a scale of 1 to 10. The attributes of each dataset should be examined to determine their contribution to the cost of building a road. For example, it is more costly to traverse steep slopes, so steeper slopes will be assigned higher costs when reclassifying this dataset. The graphics below display the results.

Reclassified slope
Reclassified slope input
Reclassified land use
Reclassified land-use input

Weighting datasets according to percent influence

The next step in producing the cost raster is to combine the reclassified datasets. The simplest approach is to just mathematically add them together. However, some factors may be more important than others. For instance, avoiding steep slopes may be twice as important as the land-use type, so you might give this dataset an influence of 66 percent and the land-use dataset an influence of 34 percent (to equal 100 percent). The following diagrams show the conceptual process:

Weighting slope
Weighting classified slope input
Weighting land use
Weighting classified land-use input

Combining the datasets

The final cost raster is created by adding together the weighted datasets.

Combining the weighted inputs
Combining the weighted inputs

The following diagram shows the final cost raster. It is the result of reclassifying the input datasets of slope and land use; weighting each by 0.66 and 0.34, respectively; then combining the weighted datasets.

Final cost raster
Final cost raster

This cost surface raster can now be used as an input into the Cost Distance or other cost tools.